Bloomberg Messaging Project Phase I





Project Start:
Project Finish:
Wed 2/1/06
Mon 3/20/06


Tasks


ID
Task Name
DurationStartFinishResource Names% Complete
1
Bloomberg Messaging System Phase I
34 daysWed 2/1/06Mon 3/20/06 0%
2
System Requirement Definition
14 daysWed 2/1/06Mon 2/20/06 0%
3
Formal Delivery
7 daysWed 2/1/06Thu 2/9/06 0%
4
Negotiation
7 daysFri 2/10/06Mon 2/20/06 0%
5
Sign Off
0 daysMon 2/20/06Mon 2/20/06 0%
6
Overall System Design
15 daysWed 2/1/06Tue 2/21/06 0%
7
Hardware
15 daysWed 2/1/06Tue 2/21/06 0%
8
System Layout
5 daysWed 2/1/06Tue 2/7/06 0%
9
Component Description
3 daysWed 2/8/06Fri 2/10/06 0%
10
Performance Metrics
6 daysMon 2/13/06Mon 2/20/06 0%
11
BOM Recommendation
1 dayTue 2/21/06Tue 2/21/06 0%
12
Software
14 daysWed 2/1/06Mon 2/20/06 0%
13
System Layout
5 daysWed 2/1/06Tue 2/7/06 0%
14
3rd Party S/W Enumeration
4 daysWed 2/1/06Mon 2/6/06 0%
15
System Flow Chart
1 dayWed 2/8/06Wed 2/8/06 0%
16
Component Description
3 daysThu 2/9/06Mon 2/13/06 0%
17
Performance Metrics
5 daysTue 2/14/06Mon 2/20/06 0%
18
System Design Doc Deliverable
0 daysMon 2/20/06Mon 2/20/06 0%
19
Off-Site Environment
20 daysWed 2/1/06Tue 2/28/06 0%
20
Location
10 daysWed 2/1/06Tue 2/14/06 0%
21
Equipt. Acquisition
10 daysWed 2/1/06Tue 2/14/06 0%
22
Network Considerations
10 daysWed 2/15/06Tue 2/28/06 0%
23
Source Control
4 daysWed 2/1/06Mon 2/6/06 0%
24
Collection Schema Generation
4 daysWed 2/1/06Mon 2/6/06 0%
25
Design
2 daysWed 2/1/06Thu 2/2/06 0%
26
Coding
1 dayFri 2/3/06Fri 2/3/06 0%
27
Peer Review
1 dayMon 2/6/06Mon 2/6/06 0%
28
Collection Schema Deliverable
0 daysMon 2/6/06Mon 2/6/06 0%
29
C-API (Search/Indexing)
20 daysTue 2/7/06Mon 3/6/06 0%
30
Design - First Draft
10 daysTue 2/7/06Mon 2/20/06 0%
31
Minimum Flow Diagram
5 daysTue 2/21/06Mon 2/27/06 0%
32
Initial Headers
4 daysTue 2/28/06Fri 3/3/06 0%
33
Peer Review
1 dayMon 3/6/06Mon 3/6/06 0%
34
Initial C-API Deliverable
0 daysMon 3/6/06Mon 3/6/06 0%
35
Software Audits
18 daysWed 2/1/06Fri 2/24/06 0%
36
Tokenizer
3 daysWed 2/1/06Fri 2/3/06 0%
37
Miroring/Remote Services
3 daysMon 2/6/06Wed 2/8/06 0%
38
VDK Functionality
12 daysThu 2/9/06Fri 2/24/06 0%
39
Hardware Performance Evaluation
31 daysMon 2/6/06Mon 3/20/06 0%
40
Hardware Research
4 daysMon 2/6/06Thu 2/9/06 0%
41
Hardware Acquisition
9 daysFri 2/10/06Wed 2/22/06 0%
42
Network Implementation
7 daysThu 2/23/06Fri 3/3/06 0%
43
Basic System Test
7 daysMon 3/6/06Tue 3/14/06 0%
44
VDK Feature Definition
1 dayFri 2/10/06Fri 2/10/06 0%
45
Load Simulation Generation
3 daysMon 2/13/06Wed 2/15/06 0%
46
Test Case Development
6 daysThu 2/16/06Thu 2/23/06 0%
47
Execute Testing
4 daysWed 3/15/06Mon 3/20/06 0%
48
SAN S/W Lock Mechanism Design
5 daysWed 2/1/06Tue 2/7/06 0%
49
Interface Of Test Harness Components
3 daysWed 2/1/06Fri 2/3/06 0%
50
Messaging
1 dayWed 2/1/06Wed 2/1/06 0%
51
Search
1 dayThu 2/2/06Thu 2/2/06 0%
52
Folders
1 dayFri 2/3/06Fri 2/3/06 0%

Resources


IDNameGroupMax UnitsPeak Units

Assignments


Task IDTask NameResource NameWorkStartFinish% Work Complete