| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 1 | Bloomberg Messaging System Phase I | 34 days | Wed 2/1/06 | Mon 3/20/06 | | 0% |
| 2 | System Requirement Definition | 14 days | Wed 2/1/06 | Mon 2/20/06 | | 0% |
| 3 | Formal Delivery | 7 days | Wed 2/1/06 | Thu 2/9/06 | | 0% |
| 4 | Negotiation | 7 days | Fri 2/10/06 | Mon 2/20/06 | | 0% |
| 5 | Sign Off | 0 days | Mon 2/20/06 | Mon 2/20/06 | | 0% |
| 6 | Overall System Design | 15 days | Wed 2/1/06 | Tue 2/21/06 | | 0% |
| 7 | Hardware | 15 days | Wed 2/1/06 | Tue 2/21/06 | | 0% |
| 8 | System Layout | 5 days | Wed 2/1/06 | Tue 2/7/06 | | 0% |
| 9 | Component Description | 3 days | Wed 2/8/06 | Fri 2/10/06 | | 0% |
| 10 | Performance Metrics | 6 days | Mon 2/13/06 | Mon 2/20/06 | | 0% |
| 11 | BOM Recommendation | 1 day | Tue 2/21/06 | Tue 2/21/06 | | 0% |
| 12 | Software | 14 days | Wed 2/1/06 | Mon 2/20/06 | | 0% |
| 13 | System Layout | 5 days | Wed 2/1/06 | Tue 2/7/06 | | 0% |
| 14 | 3rd Party S/W Enumeration | 4 days | Wed 2/1/06 | Mon 2/6/06 | | 0% |
| 15 | System Flow Chart | 1 day | Wed 2/8/06 | Wed 2/8/06 | | 0% |
| 16 | Component Description | 3 days | Thu 2/9/06 | Mon 2/13/06 | | 0% |
| 17 | Performance Metrics | 5 days | Tue 2/14/06 | Mon 2/20/06 | | 0% |
| 18 | System Design Doc Deliverable | 0 days | Mon 2/20/06 | Mon 2/20/06 | | 0% |
| 19 | Off-Site Environment | 20 days | Wed 2/1/06 | Tue 2/28/06 | | 0% |
| 20 | Location | 10 days | Wed 2/1/06 | Tue 2/14/06 | | 0% |
| 21 | Equipt. Acquisition | 10 days | Wed 2/1/06 | Tue 2/14/06 | | 0% |
| 22 | Network Considerations | 10 days | Wed 2/15/06 | Tue 2/28/06 | | 0% |
| 23 | Source Control | 4 days | Wed 2/1/06 | Mon 2/6/06 | | 0% |
| 24 | Collection Schema Generation | 4 days | Wed 2/1/06 | Mon 2/6/06 | | 0% |
| 25 | Design | 2 days | Wed 2/1/06 | Thu 2/2/06 | | 0% |
| 26 | Coding | 1 day | Fri 2/3/06 | Fri 2/3/06 | | 0% |
| 27 | Peer Review | 1 day | Mon 2/6/06 | Mon 2/6/06 | | 0% |
| 28 | Collection Schema Deliverable | 0 days | Mon 2/6/06 | Mon 2/6/06 | | 0% |
| 29 | C-API (Search/Indexing) | 20 days | Tue 2/7/06 | Mon 3/6/06 | | 0% |
| 30 | Design - First Draft | 10 days | Tue 2/7/06 | Mon 2/20/06 | | 0% |
| 31 | Minimum Flow Diagram | 5 days | Tue 2/21/06 | Mon 2/27/06 | | 0% |
| 32 | Initial Headers | 4 days | Tue 2/28/06 | Fri 3/3/06 | | 0% |
| 33 | Peer Review | 1 day | Mon 3/6/06 | Mon 3/6/06 | | 0% |
| 34 | Initial C-API Deliverable | 0 days | Mon 3/6/06 | Mon 3/6/06 | | 0% |
| 35 | Software Audits | 18 days | Wed 2/1/06 | Fri 2/24/06 | | 0% |
| 36 | Tokenizer | 3 days | Wed 2/1/06 | Fri 2/3/06 | | 0% |
| 37 | Miroring/Remote Services | 3 days | Mon 2/6/06 | Wed 2/8/06 | | 0% |
| 38 | VDK Functionality | 12 days | Thu 2/9/06 | Fri 2/24/06 | | 0% |
| 39 | Hardware Performance Evaluation | 31 days | Mon 2/6/06 | Mon 3/20/06 | | 0% |
| 40 | Hardware Research | 4 days | Mon 2/6/06 | Thu 2/9/06 | | 0% |
| 41 | Hardware Acquisition | 9 days | Fri 2/10/06 | Wed 2/22/06 | | 0% |
| 42 | Network Implementation | 7 days | Thu 2/23/06 | Fri 3/3/06 | | 0% |
| 43 | Basic System Test | 7 days | Mon 3/6/06 | Tue 3/14/06 | | 0% |
| 44 | VDK Feature Definition | 1 day | Fri 2/10/06 | Fri 2/10/06 | | 0% |
| 45 | Load Simulation Generation | 3 days | Mon 2/13/06 | Wed 2/15/06 | | 0% |
| 46 | Test Case Development | 6 days | Thu 2/16/06 | Thu 2/23/06 | | 0% |
| 47 | Execute Testing | 4 days | Wed 3/15/06 | Mon 3/20/06 | | 0% |
| 48 | SAN S/W Lock Mechanism Design | 5 days | Wed 2/1/06 | Tue 2/7/06 | | 0% |
| 49 | Interface Of Test Harness Components | 3 days | Wed 2/1/06 | Fri 2/3/06 | | 0% |
| 50 | Messaging | 1 day | Wed 2/1/06 | Wed 2/1/06 | | 0% |
| 51 | Search | 1 day | Thu 2/2/06 | Thu 2/2/06 | | 0% |
| 52 | Folders | 1 day | Fri 2/3/06 | Fri 2/3/06 | | 0% |